Mathematics · Time and Work
A can complete 1 3 of a work in 7 days and B can complete 2 7 of the same work in 10 days. In how many days can both A and B together complete the work?
- 112 3 8
- 211 7 8
- 313 1 8✓
- 415 1 7
Correct answer
13 1 8