A borrow pit soil has a dry density of 1.76 t/m 3 . How many cubic meters of this soil will be required to construct an embankment of 100 m 3 volume with a dry density of 1.68 t/m 3 ?
- 1100.00 m 3
- 2104.76 m 3
- 3110.25 m 3
- 495.45 m 3✓
Correct answer
95.45 m 3