A, B, and C working together can complete a work in 16 days. If A and B work together, they can complete the same work in 18 days. If B and C work together, they can complete the same work in 24 days. In how many days can A and C complete the same work?
- 126
- 254
- 321
- 436✓
Correct answer
36