Mathematics · Work and Time
A, B, and C together can complete a work in 54 days. B and C together can complete the same work in 56 days. B is 75% more efficient than A. If A, B, and C work together for 52 days, in how many days will B alone complete the remaining work?
- 130 days
- 234 days
- 332 days✓
- 427 days
Correct answer
32 days