Mathematics · Work and Time
A, B, and C together can complete a piece of work in 40 days. After working together with B and C for 16 days, A leaves and then B and C complete the remaining work in 40 days. In how many days can A alone complete the entire work?
- 1120 days
- 2100 days✓
- 390 days
- 480 days
Correct answer
100 days