Mathematics · Time and Work
A, B and C can finish a work in 15 days when working alternately in the same order (A, then B, then C). The efficiency of A is the same as that of B, and the efficiency of C is equal to that of A. In how many days will the work be finished if they work alternately in the order C, A and B?
- 116
- 215✓
- 314
- 412
Correct answer
15