A, B and C can do a work in 20 days, 24 days and 30 days respectively. A and B left the work 4 days before completion of the work. In how many days will the whole work be finished?
- 192 / 3 days
- 2118 / 15 days
- 3127 / 15 days
- 41014 / 15 days✓
Correct answer
1014 / 15 days