Mathematics · Time and Work
A, B, and C can complete a work in 30, 60, and 120 days respectively. A left the work 10 days before the work was completed and B left 5 days before the completion of the work. Find the number of days required to complete the whole work.
- 1190/7 days
- 289/7 days
- 3144/7 days
- 4170/7 days✓
Correct answer
170/7 days