A, B and C can complete a piece of work individually in 30, 40 and 120 days respectively. If A is helped by B and C on alternate days (B on one day and C on the next day), in how many days will the work be completed?
- 130 days
- 220 days✓
- 315 days
- 410 days
Correct answer
20 days