A and B working together can complete a work in 20 days. Had A worked at half of his efficiency and B at 6 times of his efficiency, it would have taken them 3313% of the scheduled time to finish the job. In how many days can A alone complete the job?
- 133 days
- 23323 days
- 33623 days✓
- 440 days
Correct answer
3623 days