Mathematics · Time and Work
A and B working separately can do a piece of work in 8 and 12 days respectively. If they work for a day alternately, with A beginning on the first day, in how many days will the work be completed?
- 118
- 2912✓
- 31012
- 47
Correct answer
912
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Time and Work?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Time and Work