A and B undertake to do a piece of work for ₹984. A alone can do it in 8 days, while B can do it in 6 days. With the help of C, both of them can finish the work in 3 days. How much money should be paid to C?
- 1234
- 2369
- 3492
- 4123✓
Correct answer
123