A and B can finish a work in 6 days and 4 days, respectively. A alone worked on it for 2 days. Thereafter, B joined him. How much total time was taken by them to finish the work?
- 1415 days
- 2315 days
- 3135 days
- 4335 days✓
Correct answer
335 days