Mathematics · Time and Work
A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in:
- 116 days
- 28 days✓
- 312 days
- 432 days
Correct answer
8 days