Mathematics · Time and Work
A and B can do a piece of work in 25 days and 30 days, respectively. They worked together for 6 days, after which B was replaced by P and the work was finished in the next 8 days. How long will P alone take to complete the same work?
- 130 25 days
- 215 12 days
- 325 34 days
- 433 13 days✓
Correct answer
33 13 days