Mathematics · Time and Work
A and B can do a piece of work in 12 days and 15 days respectively. They started the work together, but after some days B left the job. A finished the remaining work alone in 3 days. If A and B are contracted to do this work for Rs. 6600, find B's share of the money.
- 1Rs. 1100
- 2Rs. 2200✓
- 3Rs. 4400
- 4Rs. 3600
Correct answer
Rs. 2200