Mathematics · Work and Time
A and B can complete a work in 12 days and 6 days, respectively. They started doing the work together but after 2 days, B had to leave, and A completed the remaining work alone. The remaining work was completed in how many days?
- 19
- 210
- 38
- 46✓
Correct answer
6