Mathematics · Time and Work
A and B can complete a work in 10 days and 15 days, respectively. They started working together but after 3 days B had to leave and A alone completed the remaining work. In how many days in all was the entire work completed?
- 15 days
- 26 days
- 37 days
- 48 days✓
Correct answer
8 days