Mathematics · Time and Work
A and B can complete a piece of work individually in 20 days and 16 days, respectively. They started working on alternate days, and the entire work was completed in 17.75 days. If the total wage paid for the completion of the work was Rs. 3600, find the share of B.
- 1Rs. 2025✓
- 2Rs. 1840
- 3Rs. 2620
- 4Rs. 2750
Correct answer
Rs. 2025