Mathematics · Time and Work
A and B can complete a piece of work in 18 days and 12 days, respectively. They work on alternate days till the work gets completed. How long (in days) would it take A and B to complete the work, starting with A on the first day?
- 114.5 days✓
- 216 days
- 314 days
- 415 days
Correct answer
14.5 days