Mathematics · Time and Work
A and B can complete a piece of work in 15 days and 10 days respectively. They started doing the work together, but after 2 days B had to leave and A alone completed the remaining work. In how many total days was the work completed?
- 115 days
- 212 days
- 310 days✓
- 48 days
Correct answer
10 days