A alone can do a piece of work in 11 days. B alone can do the same work in 22 days. C alone can do the same work in 33 days. They work in the following manner: Day 1: A and B work. Day 2: B and C work. Day 3: C and A work. Day 4: A and B work, and so on. In how many days will the work be completed?
- 16 days
- 23 days
- 312 days
- 49 days✓
Correct answer
9 days