Mathematics · Time and Work
A alone can complete a piece of work in 36 hours. C and B together can complete it in 18 hours. A and C together can complete it in 24 hours. All three workers worked together for 6 hours, but then B leaves. How much time will it take for A and C to complete the remaining work?
- 18 hours
- 212 hours✓
- 39 hours
- 410 hours
Correct answer
12 hours