A 6-stage arithmetic pipeline processes a batch of 500 arithmetic operations. The clock cycle time per stage is 3 ns. Assuming no pipeline stalls, what is the total execution time taken to complete the batch?
- 13,015 ns
- 21,503 ns
- 31,509 ns
- 41,515 ns✓
Correct answer
1,515 ns