Computer · Traffic Engineering
A 3-phase traffic signal at a 4-legged intersection is designed with 6 traffic movement groups (A through F), where A, C, D, and F are straight/through flows, and B and E are right-turning flows. Consider the following phase combinations: Scheme W: Phase-I (A, B); Phase-II (D, E); Phase-III (C, F) Scheme X: Phase-I (A, D); Phase-II (C, F); Phase-III (E, B) Scheme Y: Phase-I (A, D); Phase-II (C, E); Phase-III (B, F) Scheme Z: Phase-I (A, B); Phase-II (E, F); Phase-III (C, D) Identify the phasing scheme that is NOT recommended due to critical traffic conflicts.
- 1Z✓
- 2W
- 3Y
- 4X
Correct answer
Z
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Traffic Engineering?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Traffic Engineering