Electrical Engineering · Transformers
A 25 kVA, single-phase transformer has 250 turns on the primary and 40 turns on the secondary winding. The primary is connected to a 1500 V, 50 Hz AC supply. What are the full-load primary and secondary currents?
- 1Primary current = 25.0 A, Secondary current = 60.0 A
- 2Primary current = 10.0 A, Secondary current = 150.0 A
- 3Primary current = 12.5 A, Secondary current = 120.0 A
- 4Primary current = 16.67 A, Secondary current = 104.2 A✓
Correct answer
Primary current = 16.67 A, Secondary current = 104.2 A
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Electrical Engineering?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Transformers?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Electrical Engineering · Transformers