Mathematics · Time and Work
8 men can complete a work in 12 days. They started the work and after 5 days, 5 men left. In how many days will the remaining work be completed by the remaining men?
- 118 2 3✓
- 223 2 3
- 325 1 3
- 420 1 3
Correct answer
18 2 3