Mathematics · Time and Work
75 workers could complete only one-third of a work in 20 days. It is desired that the remaining work be finished in the next 30 days. How many more workers should be employed to complete the work in the desired time?
- 1225
- 225✓
- 3300
- 4100
Correct answer
25