Mathematics · Time and Work
6 men and 4 boys can finish a work in 20 days, and the same work is finished in 24 days by 4 men and 6 boys. In how many days can 2 boys and 1 man finish the work?
- 187.5✓
- 285.7
- 378.5
- 475.8
Correct answer
87.5