Mathematics · Time and Work
40 men can complete a piece of work in 18 days. 9 days after they start working together, 5 more men join them. How many days will they now take to complete the remaining work?
- 17 days
- 26 days
- 38 days✓
- 49 days
Correct answer
8 days