Mathematics · Time and Work
18 women can complete a piece of work in 12 days, and 12 men can complete the same work in 9 days. In how many days will 8 men and 8 women complete that work together?
- 18 days
- 212 days
- 36 days
- 49 days✓
Correct answer
9 days
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length Mathematics mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Time and Work?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Time and Work