Mathematics · Work and Time
10 men, working 8 hours a day, complete a piece of work in 12 days. 8 women, working 12 hours a day, complete the same work in 8 days. If 6 men and 6 women work 6 hours a day on alternate days, and the men start working on the first day, then the work is completed in how many days?
- 11185 days✓
- 21285 days
- 31385 days
- 41085 days
Correct answer
1185 days
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Work and Time?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Work and Time