Mathematics · Work and Time
10 boys take 15 days to complete a work which can be completed by 6 men in 10 days. 15 men started working and after 2 days, 10 men left and 10 boys joined the remaining 5 men. How many days will they take to complete the remaining work?
- 110 3✓
- 26
- 316 3
- 44
Correct answer
10 3
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Work and Time?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Work and Time